Gault Road:
Week of July 2nd:
Road closures are scheduled from the intersection of John
Goffe to the roundabout on Meetinghouse Road M-F 6:30AM-4:30PM. The
Contractor will be placing select gravel materials during this period.
Once complete, fine grading and paving operations will commence and are
tentatively scheduled at the end of the week for the entire Gault Road
reconstruction area. Operational signs will be in place to assist with traffic
control.
Week of July 9th:
Cleanup, loaming and seeding operations are scheduled.