Week of August 28th:Week of August 28th:
Week of August 28th:
Start Replacement of
outdated and failing drainage pipes.
Expect daytime delays and detours during this operation. Flaggers and operational signage shall be in
place to assist motorists.
Week of September
3rd:
Complete installation
of new drainage pipes, and install new headwalls. Patch trenches and crack seal the remainder
of the road. Expect delays and detours
during this operation.
Start replacement of outdated and failing drainage pipes. Expect daytime delays and detours during this operation. Flaggers and operational signage shall be in place to assist motorists.
Start replacement of outdated and failing drainage pipes. Expect daytime delays and detours during this operation. Flaggers and operational signage shall be in place to assist motorists.